- Posts: 74
- Thank you received: 0
babynus wrote:
You can : just enter assigned work as hours... Planning will take it into account.How can I deal with Acitivities which will only take about a few hours at most?
Don't mind about duration : projector always calculate durtion in days... so smallest duration is 1 day, even if it really takes 1 hour.
babynus wrote:
Yes. It is plroject management, not exploitation management.Are Activities supposed to be larger chunks of work? If so, how do I model small "Activities" in ProjeQtor?
Good scale for tasks, in my opinion is 5-10 days.
Please Connexion or Create an account to join the conversation.
No, duration will be displayed as 1 day, but planned work will take just 1 or 2 hours.However this means that Activities estimated to take only 1 or 2 hours cannot be used in planning as such - for planning, they will always take at least about a day, right?
This is exactly why we have "Tickets".So if I have a bunch of smaller issues / todos, I could combine them into a single, larger Activity and document them there.
However, I then would have to manually keep track about the resolved and still open TODOs within this Activity. An example would be an Activity which has 10 sub-TODOs.
Maybe I could use Tickets to model this? Those could then also be linked to an Activity for time/effort tracking, if I understood the manual correctly?
You just have one activity. All ressources are assigned to the acitivity. Each resource enter some real work on the ticket... That's easy (see button "Dispatch work" for more detailed input mode)How is it handled in this case if the tickets are assigned to and resolved by different resources - will the Activity stay unassigned, or will each Ticket have to be linked to an Activity assigned to the same responsible Resource as the Ticket?
Please Connexion or Create an account to join the conversation.
babynus wrote:
No, duration will be displayed as 1 day, but planned work will take just 1 or 2 hours.However this means that Activities estimated to take only 1 or 2 hours cannot be used in planning as such - for planning, they will always take at least about a day, right?
Please Connexion or Create an account to join the conversation.
Please Connexion or Create an account to join the conversation.
Please Connexion or Create an account to join the conversation.
Please Connexion or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.