Hello,
I found out that we can save a baseline for a planning and superimpose it with the actual planning.
My probleme is i can't figure out how it work and i can't display the saved baseline on my planning. Am i doing something wrong ?
To save a baseline click on button " save a baseline of planning " then select one project and name your baseline.
Once saved select your baseline under " show baseline " on buttom or on top. ( Be careful of you current selected project, it has to correspond to your baseline project )
The Planning screen has these buttons to save a baseline and to display saved baselines.
You can compare your current planning against TWO baselines simultaneously.
The Gantt chart shows three sets of bars simultaneously.
One of them appears above the current planning bars, and the other appears below the current planning bars.
If you planning has changed by a wide margin, you may have to pan across the Gantt chart to find your baseline!
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Paramétrages de cookies
×
Cookies fonctionnels
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Veuillez vous connecter pour voir vos activités!
Autres cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.