Use "bill" item for billing mode "t&m"
Billing mode is defined on project type.
Project type is selected on project.
Then :
- you define activity price : selling daily price for activity type
- you add on bill 1 line per resource : select a priod and activity price
ProjeQtOr will retreive all "billable" work for resource on period for given activity type.
I create a new Activities Type name "Selling Task"
I create a project with type set to "Time & Materials"
I create an activity on previous project with "Selling task" activity type
I declare real work allocation on the task (3 days with a cost of 300€ for ressource pierre), visible in the activity and in the project.
I declare an activity price on previous project with activity "selling task", price 50€.
I create a bill and enter 1 line per ressource for the period and activtity.
Cost is 300€ (I gues daily cost for resource is 100€ per day) but bill is 3xactivity price=150€ (activity price is 50€)
So you sell resource less than what they cost
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Paramétrages de cookies
×
Cookies fonctionnels
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Veuillez vous connecter pour voir vos activités!
Autres cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.