We have two teams, one working in India and the other working in the Gulf.
I need to create another calendar, which differs from the default calendar in the following ways:
1. There is a time difference of 2 hours (India is 2 hours ahead of Gulf)
2. The weekly off days are different (we have weekend on Sat+Sun, and in the Gulf they have weekend on Fri+Sat)
3. The national holidays are different in the respective country.
I already have set the global parameters for my default calendar.
How do I create one more calendar with these changes?
1. There is a time difference of 2 hours (India is 2 hours ahead of Gulf)
No way. ProjeQtOr does not know user timezone. It is subject of Ticket #2596
2. The weekly off days are different (we have weekend on Sat+Sun, and in the Gulf they have weekend on Fri+Sat)
3. The national holidays are different in the respective country.
In "Environmental parameters">>"Calendars", create new calendar, then select this calendar for resources.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Paramétrages de cookies
×
Cookies fonctionnels
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Veuillez vous connecter pour voir vos activités!
Autres cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.