Hello,
I have a mini project with about 10 task and 207 assigned hours ( seee screen capture) and when i produce the S curve , I see only 29 hours for the coût budgetiser du travail planifié (see s curve figure). Shouldn`t the 207 assigned hours be equal to the planned value ( coût budgetiser du travail planifié)? Am I missing something?
Regards
Thanks
Mayby a conversion issue.
It seems S-curve is displayed in days but unit displays "h" for hours.
Can you confirm that it is correct if unit is not jours but days ?
Hello,
It does not seem to be a conversion issue since 207 assigned hours represents 25.8 days of effort ( at 8 hours per day) and the S curve displays 30 hours of planned work.
Would you have any suggestions?
Regrads
Thank for your support
Hello Babynus,
Have you had the time to investigate the problem? I have added notes to my discussion on the forum and I am not shure you have received them.
Thank you in advance for your support
Regards
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Paramétrages de cookies
×
Cookies fonctionnels
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Veuillez vous connecter pour voir vos activités!
Autres cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.