18 Déc 2023 15:02 #1 by Coasterman
Hello

I enabled and disabled things shown in my Today Page configuration.
As soon I enabled "What's new", my today page remind blank with hidden buttons from the gantt menu in the right top corner.
I couldn't change anything anymore until i switched to the old view where it showed me "unknow" as enabled.
As soon i uncheckt that unknown i could see again my today page in the new design.

I went back and clicked on the red "x" of the unknowns and they reapeared at the bottom with and were enabled.
I switched to the new view again and also the  Whats new was shown, but not my reports. I disabled "Whats new" and my reports appeared.

Starnge, but lucky the old design still exist in this case...


Attachments:

Please Connexion or Create an account to join the conversation.

More
19 Déc 2023 12:39 #2 by babynus
Replied by babynus on topic Unknow today scope
Hi,

I could not reproduce the issue you're facing.
Do you have any error in log file or in browser console ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
19 Déc 2023 14:21 #3 by Coasterman
Replied by Coasterman on topic Unknow today scope
I can partially reproduce it.

Since i clicked on the "x" symbols what I reported, the today area doesn't get blank anymore, but the reports are not displayed when "What's new" is enabled
There is no log entry in projeqtor

Attached you can find the browser consol and problems.

 
Attachments:

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.042 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.