11 Avr 2022 08:34 #1 by chandrashekhar
Hi Team,

In Planning Screen, When I am going to add dependency in some activities at that time I am feeling helpless that it is not showing wbs. Due to that, I just need to change the activity name which I don't want.!
If this feature (show wbs too with activity id) will be added while adding dependency it will be Good.

Thanks.

Please Connexion or Create an account to join the conversation.

More
11 Avr 2022 11:38 #2 by babynus
In the pop-up, biside list of activities, click on the "search" button (magnifyer icon)
You'll be able to see wbs in the list

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Avr 2022 12:42 - 11 Avr 2022 12:43 #3 by chandrashekhar
Thanks for reply.
I have tried as you suggested but it is not showing any wbs in that list. Please find attachment for reference.
Attachments:
Last edit: 11 Avr 2022 12:43 by chandrashekhar.

Please Connexion or Create an account to join the conversation.

More
11 Avr 2022 13:54 #4 by babynus
You need to add the WBS columns on activity screen befor opoening the pop-up

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Avr 2022 14:26 #5 by chandrashekhar
I am already doing so, but it is not showing wbs in help!. Please find attachment for reference.
Attachments:

Please Connexion or Create an account to join the conversation.

More
11 Avr 2022 14:49 #6 by babynus
You display WBS in Gantt view, noty is Activity view (look for Activity screen)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.