Hello,
I've got a project with the administrative type (so anybody can enter work on it). This project has two activities and now i want to import work on these activities. The problem is that when importing work we need the id of the assignement (idAssignment) which is not created on administrative project because everyone can access it. How can i do it ? Do i have to assign every resources to these activites?
In fact, with administrative projects assignment is automatically generated when user opens Timesheet screen.
So for every using having opene the timesheet screen since creation of administrative projects, the assignement exists.
Otherwise, yes, you have to create assignment.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.