12 Apr 2018 17:40 #1 by Bena
Hello,

Is it possible to add a delay on a link between activities in calendar days, not in working days ?

Thanks for your wonderfull app :)

Regards.

--
Bena

Please Log in or Create an account to join the conversation.

More
12 Apr 2018 18:45 #2 by babynus
No, delay is alway in "open days"

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
14 Apr 2018 08:00 - 14 Apr 2018 08:01 #3 by Bena
In fact, I need, for legal constraint, to wait X days (not open days) after an activity.
Currently, I choose the strating date of the following activities but of course, I have to change it manually when the planification of the previous task change.
Do you have an idea about doing that in a better way so that the next activity move automatically ?

--
Bena
Last edit: 14 Apr 2018 08:01 by Bena.

Please Log in or Create an account to join the conversation.

More
14 Apr 2018 10:05 #4 by babynus

Do you have an idea about doing that in a better way so that the next activity move automatically ?

As of today, there is no way to do this.
Delays are always in open days.
What you want would need an evolution. Two possibilities :
- New planning mode "fixed calendar duration" (similar to "fixed duration" but in calendar days, not working days)
- Possibility to define that delays on dependencies are in "calendar day" instead of "working days" (new checkbox in the definition of dependency)
Possbily both evolutions could be done.

I recorded both as Tickets #3318 and #3319
Sure this evolution will have very low priority in our roadmap.

If you need these, you may consider sponsoring the devs to have them in the next release of ProjeQtOr.
Please contact us through the contact for to get a quote for the devs.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.