does anyone have a good proposal how to insert time buffers between Projects.
Lets say we need more time in the first Project. This should be compensated by a buffer which was already planned in the beginning So the Project takes longer and the buffer is automatically descreased. Also the ressource which uses more time is used by this buffer.
As a result the follwing projects are not moved due to real work allocation, which takes more than expected.
My own idea is a separat activity for which the ressource is assigned for some time at the end of the project, and always if it needs more time than the assigned work, it books it on the buffer. But I think that may be not the best ways to do.
There is no such "buffer" mecanism in projeqtor.
But you can simply add milestone for start date of next project to have it start not immediately after first one, but at a given date...
You can also define allocation start date for the resource to the project so that it won't be used before.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.