ProjeQtOr free project management software - Why is the "Due dates -> initial date" not "read only"? - ProjeQtOr
 

Why is the "Due dates -> initial date" not "read only"?

More
12 Jul 2017 12:08 #1 by Kitcat711
Working on the ticket Due dates, since the user can change the "planned date" and the "initial date" is automatically provided, why the user can also modify the "initial date"?

I don't get the point, and, since initial date are linked to SLA's (in my case) I would not prefer to see it moving during the time the ticket is open.

Please Log in or Create an account to join the conversation.

More
12 Jul 2017 14:17 #2 by babynus
It is a good point of view.
But due date must be set at least once ... so cannot always be readonly.
And it you enter wrong value at first input, then you should be able to correct it.

But I aggree that is due date is calculated from ticket delay, it should then be readonly.
This is registered as Ticket #2865 and should be developped with ticket #1547 (Define delay for tickets per project)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: Kitcat711

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.029 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.