How to create another default calendar?

More
05 Jul 2017 09:18 #1 by NarayanAras
Hi

We have two teams, one working in India and the other working in the Gulf.

I need to create another calendar, which differs from the default calendar in the following ways:
1. There is a time difference of 2 hours (India is 2 hours ahead of Gulf)
2. The weekly off days are different (we have weekend on Sat+Sun, and in the Gulf they have weekend on Fri+Sat)
3. The national holidays are different in the respective country.

I already have set the global parameters for my default calendar.
How do I create one more calendar with these changes?

Please Log in or Create an account to join the conversation.

More
07 Jul 2017 16:26 #2 by babynus

1. There is a time difference of 2 hours (India is 2 hours ahead of Gulf)

No way. ProjeQtOr does not know user timezone. It is subject of Ticket #2596

2. The weekly off days are different (we have weekend on Sat+Sun, and in the Gulf they have weekend on Fri+Sat)
3. The national holidays are different in the respective country.

In "Environmental parameters">>"Calendars", create new calendar, then select this calendar for resources.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.