13 Jan 2021 05:10 #1 by rainbow
Hi,

I tried to import MS project in demo V9.0.2 and found out that the start and end dates are not filled in to the validated and requested dates.

 

Moreover, I would like to ask whether it is possible to supposed to import notes from MS project as well?

Thanks,
Rainbow
Attachments:

Please Log in or Create an account to join the conversation.

More
13 Jan 2021 19:41 #2 by babynus

I tried to import MS project in demo V9.0.2 and found out that the start and end dates are not filled in to the validated and requested dates.

Yes, change of validated dates should be done through Projeqtro feature "Validate planning"

Moreover, I would like to ask whether it is possible to supposed to import notes from MS project as well?

I was note aware you coulde save note on MS-Project...
We'll have a look.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
14 Jan 2021 07:35 #3 by rainbow
Hi,

Could the start and end dates in MS Project be imported as validated/requested dates in order to keep the initial requested plan dates? 

FYI, for the notes, it is a defined field in MS Project.
 

Thanks,
Rainbow
Attachments:

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.042 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.